Mahshahr Export Port Project
The plan of Mahshahr Export Port was handed over to Machine Sazi Arak, Khatam-ol-Anbia and Rampco companies via National Iranian Oil Products Distribution Company as the owner of project in three parts of land, offshore and pipelines in the form of three EPC projects.
The project site of the Mahshahr Export Port is located at a distance of 11 kilometers from Imam Khomeini port and has 6 berths for loading oil products. Products distributed from this port include gasoline, gasoline, petrol, oil, aromatics and naphtha. The engineering phase of this project involves basic, detailed and executive engineering in all engineering disciplines such as civil, mechanics, piping, electricity and telecommunications, instruments and safety. Due to the necessity of port service, the important point in designing this project is design of the project in such a way that, while optimizing the systems, the existing systems of port was fully used. In this project, the basic engineering documents and engineering technical documents for procurement and construction with number of 2700 documents were produced and were approved by the employer. Also about 700 companies were used by domestic and foreign manufacturers to supply the equipment.
In this project, 32 hectares of Majidieh logs were digested and dried then recovered by soil and water so consolidated up to 95%. Equipment for the export of fuel oil and gasoline and bunkering of fuel oil in this section was designed, supplied and installed.
The outline of the EPC works done in this project is as follows:
Engineering and implementation of protection dikes:
Engineering and implementation of protection dikes to cut off seawater with an area of 1200 m and an altitude of 3+ m above the surface of the area
Gasoline storage tanks:
Construction and installation of five 100,000 barrels floating roof tanks for storage of gasoline
Land extraction from the sea of 32 hectares and pre-loading with soil and water
The extraction operations in this project were carried out using drainage and loading procedures. In order to implement vertical drainage, the special towers were used which two of these towers were first made in Machine Sazi Arak in Iran. In addition, to load the soil to consolidate the land, more than 1.5 million square meters of soil was used, with loading height in some places reach to 12 meters, and to accelerate the time and lack of sufficient soil, part of the area 4 units of fixed roof tank were loaded with water of 250 barrels. Previous experience has shown that preloading with soil has more costs in addition to time. It seems that pre-loading method with water be an appropriate alternative to the soil. In this method, after the construction of the tanks, they were continuously and daily stored for 45 days and after a month of storage of water in the tanks, evacuation was carried out.
Gasoline and fuel oil storage tanks:
Construction and installation of twelve 250,000 barrels fixed storage tanks for storage of fuel and gasoline
Transferring water:
Construction of the 8-inch water pipeline with length of 11 km
Piping
The collection of old pipelines and the implementation of new pipelines in the export port with a volume of more than 400,000 dia/inch and at the same time maintenance of port servicing.
Power line:
Construction of KV 132 transmission line to Mahshahr Export Port and construction of KV33 / 132 power station
Substation:
Development of 132/400 kV power supply
Fire extinguishing system:
Design and implementation of a fire extinguishing system including the procurement of tank fire fighting and piping operations
Terminal control system:
Design and manufacture of the largest control system of oil terminals in Iran (DCS & ESD), which is the largest control system designed for oil terminals in Iran, to fully control and automate all oil exports and imports
Electrical Equipment:
Installation of electrical equipment and construction of substations for power transmission and distribution
Electrical Equipment:
Installation of electrical equipment and construction of substations for power transmission and distribution
Electrical Equipment:
Construction of 11,000 square meters of building including industrial buildings (control room, substandard) and non-industrial and service buildings (restaurant, guest house, fire department) construction of 13 kilometers of highways and roads within the boundary of the export port, execution foundation and Band walls and landscaping and surface water collection System
Engineering, Procurement and Construction of Karun 4 Bridges This bridge is the largest arch bridge in the country for connecting the Izeh road to Shahrekord and installed on the reservoir of the Karun 4 dam. Engineering, procurement of raw materials, construction and installing parts and commissioning of this bridge was carried out by Machine Sazi Arak within 20 months. The bridge is arched from below and is constructed as a leading nose on both sides.
Owner: Iran Water and Power Resources Development Company
Project Overview:
Bridge type: Arch
Deck Type: Orthotropic
Deck length: 380 meters
Arc span: 300 meters
Arch deflection: 70 meters
Deck width: 11.8 m
Weight: 3800 tons
Engineering, Procurement and Construction of Karun 4 Cable Stayed Bridges for Oil Pipeline
This project includes engineering, procurement, construction and commissioning of a large cable stayed bridge with a length of about 380 meters on the Karun 4 dam for passage of oil and gas pipelines which was carried out by Machine Sazi Arak Co. within 18 months
Owner: Iran Water and Power Resources Development Company
Project Overview:
Bridge type: Cable Stayed
Deck Type: Orthotropic
Total length of the bridge: 380 m
Width: 9.2 m
Weight of deck and pylons: 1900 tons
Weight of cable: 100 tons
The bridge is currently considered a major bridge in the country, which will be used in nomadic seasons. A large amount of landfill and transhipment operations were carried out to construct the bridge and transport pipelines, and about 19 km of access roads were built.
Borzoueh Perochemical MSA activities in Borzoueh petrochemical are as follows: civil and structure activities and engineering, procurement and construction of 6 spherical tanks with capacity of 9000 m different capacities and 4 fixed roof storage tanks and 8 floating roof storage tanks including piping ,firefighting, mechanical equipment(pumps, drums, thermal transformers, compressors and etc.), electrical activities, instrumentation and insulation equipment with a total weight of 34000 tons.
South Pars gas field development phase 14 (SPGFD Phase 14) Employer: National Iranian Oil Company
Project Specifications:
Designing, constructing, installing and commissioning four sea platforms equipped with 44 wells including 2 appraisal wells, 2 vertical wells and 40 development wells. These platforms also provide sewage water separation facilities along with gas from platforms and MEG injection and other related equipment.
Design, implementation and commissioning of two 32-inch marine pipelines to connect the platforms to the refinery with length of 211 km.
The design, implementation and commissioning of two 18-inch sea-line pipelines, with length of 16 km, and installation of 4-inch sea pipelines on the pipelines 32" and 18" for the transfer of glycols (inhibitor) with length of 228 km.
Design, construction and commissioning of a refinery on 170 hectares of land in the Pars-2 region including sour gasification facilities, extracting gas condensate, producing and exporting LPG, Ethan and Sulfur.
Machine Sazi Arak as one of the members of the Consortium Phase 14 of the South Pars gas field development project, with a contract with a value of US$ 240,000,000 with a share of 4.57 % of the total plan, was responsible for providing the fixed equipment of the refinery.
The scope of work of Machine Sazi Arak Co. includes construction engineering (after receiving mechanical data sheets), the provision of raw materials of various types of sheets, pipes, profiles, forging, fittings and etc., the construction of a workshop of equipment and shipment
Construction engineering, raw material v, construction workshop, transportation and delivery of 165 tanks.
Engineering, construction, material procurement, construction workshop, transportation and delivery of 40 towers.
Construction engineering, raw materials procurement, construction of a workshop, transportation and delivery of 16 reactors.
Engineering, construction, material procurement, workshop, transportation and delivery of 81 heat exchangers.
Engineering, manufacturing, supplying, manufacturing workshops, shipping and delivering 52 aircrafts
Contractor: A consortium of 8 members with the leadership of IDRO is as follows:
1. Iranian Industrial Development and Renovation Organization (Consortium Leader) - (IDRO)
2. Iranian Offshore Engineering and Construction Company (IOEC)
3. Iran Industrial Project Management Company (IPMI)
4. Iranian Offshore Shipping and Offshore Industrial Complex (ISOICO)
5. Iran Power Plants Management Company (MAPNA)
7. Iranian National Drilling Company (NIDC)
8. Paybandan Co.
Supplementary plan of Mahshahr export port - construction of sulfur wharf
The project aims to construction, installation and commissioning of facilities equipment and machineries for storage, and the annual export of 1,000,000 tons of produced sulfur granules in refineries of National Iranian Oil Company (NIOEC). The description of Machine Sazi Arak's services includes all design and engineering activities, procurement, construction, installation, execution, technical inspection, commissioning and final delivery.
In this regard, after conducting studies and geological experiments and preparing land improvement methods, the design and engineering of facilities and structures such as the bascule, drainage station (hopper) and sulfur storage facility as well as the transmission machinery including feeders, systems conveyor and weighing containers and related structures, tripper car, reclaim, and ship loader, as well as electrical and instrumental equipment and central control system, buildings, installations and ventilation, lighting, and cathode protection, etc. is done. According to safety considerations and environmental issues such as fire extinguishing systems and dust collectors and others. After the construction and equipping of workshops, due to the financing problems in Oil Ministry, who is the owner of project, the project has to stop.
|